Solution: The review found some areas of the silo that did not comply. Deacon Engineers detailed proposed modifications to enable the silo to comply.
Project: 360m3 Sludge Silo
Location: Oxley Creek WWTP
Timeframe: March – April 2009
Challenge: Design review and verification of a 360m3 Sludge Silo to AS1170-2002 Structural design actions & AS4100-1998 Steel structures.
Services: Design Verification and FE Analysis
Solution: The review found some areas of the silo that did not comply. Deacon Engineers detailed proposed modifications to enable the silo to comply.